Project: Supply, Install & Operation of 18m3 per day RO Plant to provide water at L. Gan, Thundi avah (tsunami reconstruction site)
Client: Moreway Arunexello (JV) Pvt. Ltd.
Duration: 10 Months
Value: MVR 549,915.75
Description: Supply and installation of one RO plant with a total production capacity of 18 m³/day. This includes the installation of the RO plant, feed water intake works, feed pumps, multimedia filter (MMF) system, bag filter filtration, transfer pumps, feed tank installations, and HDPE storage tank installations.