Project: Design and Build Basis for Construction of Water Supply Facilities in Th. Veymandoo
Client: Ministry of National Planning, Housing & Infrastructure
Duration: 720 Days
Value: MVR 36,761,383.00
Description: The project includes surveying works, EIA studies, initial and final design works, and the construction of an RO facility building. It involves the development of two boreholes, installation of two drinking water tanks (300 m³ each), and one rainwater collection tank (360 m³). Additionally, it includes the installation of two RO plants, each with a capacity of 75 m³/day, and the laying of a water network spanning 9,911 m with 337 house connections. The project also covers 1,520 m of rainwater network installation, including a rainwater treatment UF system, brine outfall works, and solar PV installation works